Some Slippage but it’s Good News
Mar 17, 2015
Not so! For I’ve been given more up to date information by Connecting Cumbria which indicates better than planned coverage will be achieved before the end of the project:
LA12 8HF & Oxen Park |
Greenodd cabinet 1 |
Early Summer 2015 |
Newby Bridge exchange |
8 cabs planned |
5 planned for Early Summer 2015, 3 planned for early Winter 2015 |
Greenodd exchange |
4 cabs planned |
2 planned for Early Summer 2015, 2 planned for early Winter 2015 |
Satterthwaite exchange |
1 cab planned |
Early Summer 2015 |
Torver |
Coniston cabinet 1 |
Early Summer 2015 |
Lowick Bridge exchange |
2 cabs planned |
2 planned for Early Winter 2015 |
(Torver & Lowick Bridge were potentially two ‘not spots’ - the latter would have implications for connections to the Nibthwaite area of our parish).
The Connecting Cumbria project overall is hitting its targets with some 67% of the County’s premises now able to get SFBB via either BT’s commercial roll-out or the Connecting Cumbria project.